This posting has an updated SCHEDULE...
We are looking for some committed help to get new concrete teepads
installed on the Rec Course during May. We understand that this is an
aggressive schedule but this will be necessary to get it done in time.
We also understand that this is during the week but that's when the
park maintenance crew and the concrete trucks are available.
Other things will be done on the course (like a new Bulletin Board /
Storage Shed / Fairway Signs / Etc.) that will take up additional
efforts later, but the TeePads are our primary concern.
Here's the quick rundown on the work schedule that we agreed with the
park for the next month or so in order to have the concrete teepads by
the Keystone Games......
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Friday May 4
At Pinchot Wood Shop Making TeePad Frames
Friday May 11
Backhoe on the course digging out teepads and
putting stones in as necessary for the base
Sunday May 13 (All Day)
On the course framing at 12 teepads for concrete
Monday May 14 (Evening)
Complete any remaining work on the framing
Wednesday May 16 (Morning)
Concrete truck delivers to Course where skidloader
and manual labor available for getting concrete
to 6 of the teepad frames
Friday May 18 (Morning)
Concrete truck delivers to Course where skidloader
and manual labor available for getting concrete
to the remaining 6 of the teepad frames
Sunday May 20 (All Day)
Teardown the first 6 poured TeePads - Reset these
frames for the final 6 Teepads
Backfill around first 6 Teepads and landscape area.
Monday May 21 (Evening)
Complete any additional setup of Frames for 6 TeePads
Tuesday May 22 (Morning)
Concrete truck delivers to Course where skidloader
and manual labor available for getting concrete
to the remaining 6 of the teepad frames
Friday May 25 (All Day)
Teardown the last 12 poured TeePads
Backfill around Teepads and landscape area.
Sunday May 20 (All Day)
Backfill around Teepads and landscape area.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
We are looking for helpers to place the concrete (moving it about
within the frame to fill the space evenly), pull the reinforced grid
into place with rakes, and rough level the concrete in the frame with
a 2x4 screed.
Helpers should have high rubber boots to protect your legs from the
concrete. We have some extra rakes and shovels if you don't have any
to bring.
ALSO, if anyone has EXPERIENCE finishing concrete, YOUR HELP WOULD BE
GREATLY APPRECIATED.
Please contact Don Dillon or me (Ken Lemkelde) as soon as possible if
you are able to help make this project happen on schedule.
Thanks for your support in the past and a pre-thanks to those who are
willing to pitch in now.
Ken(at)PinchotDiscGolf.com