RallyCross work day - Saturday, November 20, 10am - 2 pm. I have
basketball practice (Robby) until 10 and a birthday party (Robby's
friend) at 2:30 so the times will be hard fast.
Tasks:
1. Spread stone. I think we need some to fill in the large erosion
rut in the NW corner. We also can use some along the wooded area on
the S side. We should put some in the wet area near the start line.
The esses in the middle down to the dip. How many loads? One or
two?
2. Straw bale wall along the road.
3. Tear down the long straw bale wall in the SE corner.
Please come out and help. Saturday should be a nice day (for late
November) and we can get set up for next season very quickly.
thanks,
Bruce
|